Transportation started in Spain. From Madrid to Valencia´s port.
Once in the Valencian port, the steel items were packaged. Appropriate packing lists, exports documents, labelling and shipment control were also prepared in the port.
On the 4th of September, the ship moored in the port and the loading works started.
1.163 containers for 2.600 tons of steel
On October, 8th, the unloading works of the vessel begun in the Iraqi port of Umm Qasr and the transport to the Al Rusafa plot initiated.
By October, 15th, all steel items reached the site after a 6oo km trip from the port to our plot.
279 trucks were requested to transport the structural steel completely from the Iraqi port to Al Rusafa plot.